Kelle Carpet and Trim installs carpet in commercial offices. Peter Kelle has been very concerned with the amount of time it took to complete several recent jobs. Some of his workers are very unreliable. A list of activities and their optimistic completion time, the most likely completion time, and the pessimistic completion time (all in days) for a new contract are given in the following table: This exercise contains only . Based on the given three time estimates, the expected times and variance for each of the activities are: (Round your responses to two decimal places.)Explanation / Answer
Activity a m b Expected time Variance A 2 5 8 5.00 1.00 B 3 4 5 4.00 0.11 C 1 2 3 2.00 0.11 D 6 7 8 7.00 0.11 E 3 5 7 5.00 0.44 F 7 10 15 10.33 1.78 G 1 2 3 2.00 0.11 H 3 5 7 5.00 0.44 I 11 12 13 12.00 0.11 J 14 16 18 16.00 0.44 K 3 7 11 7.00 1.78 Expected time=(a+4m+b)/6 Variance=((b-a)/6)^2
Related Questions
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.