Academic Integrity: tutoring, explanations, and feedback — we don’t complete graded work or submit on a student’s behalf.

Francisco is planning a vacation to Germany. A variety of activities must be com

ID: 459625 • Letter: F

Question

Francisco is planning a vacation to Germany. A variety of activities must be completed before his departure. The following table describes the relationships between these activities:


                    Immediate
Activity     
Predecessors
     A                   -
    B                   -
     C                   -
     D                  A, B
     E                  C
     F                   D, E
     G                  E
     H                  F, G
      I                   F
     J                   I, H

Francisco was also able to estimate the activity times as shown in the table below:

Activity         Time (Days)
     A                      3
     B                      4
     C                      5
     D                      3
     E                      2
     F                      1
     G                      4
     H                      3
     I                       2
     J                      5

Considering the information above, what is the earliest finish time for activity E? (Points : 3)        5 days
       6 days
       7 days
       8 days

Explanation / Answer

Activity E is preceded by activity C . The earliest start for activity E is the early finish of activity C . The early finish of activity C is 5 days . The early finish for activity E is = early start + activity time.

Early finish for activity E = 5 + 2

Early finish for activity E = 7 days .

Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at
drjack9650@gmail.com
Chat Now And Get Quote