QUESTION 21 For bidding purposes, a _______________ is evaluated based upon area

ID: 460797 • Letter: Q

Question

QUESTION 21

       For bidding purposes, a _______________ is evaluated based upon area measured.

       Fencing

       Earthwork excavation

       Sewer lines

       None of the above

QUESTION 22

       In general, it is recommended to permit the inspector to order the contractor to stop operations.

True
False

QUESTION 23

       In federal agency projects, it is the inspector's responsibility to determine the specific needs of the types of construction records that must be established and maintained throughout the project.

True
False

QUESTION 24

       In general, soil is classified as _______ grained if most of its sample weight passes the #200 sieve.

       Fine

       Medium

       Smooth

       Coarse

QUESTION 25

       It is recommended that the inspectors assumes contractor' s possible mistakes rather than deliberate dishonesty and poor work.

True
False

QUESTION 26

       It is possible to allow significant deviations from plans and specifications without a change order provided that no cost or time extension is involved.

True
False

QUESTION 27

       It is acceptable to use the number of truckloads of loose material in determining earthwork volume.

True
False

QUESTION 28

       According to OSHA, a cohesive soil is classified as type ____.

       A

       B

       C

       D

  QUESTION 29

       If the subcontractor allowed his/her crew to be exposed to hazards that could cause serious physical harm or death, who should be held liable for that?

       The designer

       The subcontractor

       The General Contractor

       Both of b and c

QUESTION 30

       In federal contracts, a CQC representative is responsible for conducting all inspections.

True
False

Explanation / Answer

21. For bidding purposes, a earthwork excavation is evaluated based upon area measured. The area thus measured will be evaluated while determining the costs involved and hence the bidding.