QUESTION 21 For bidding purposes, a _______________ is evaluated based upon area
ID: 460797 • Letter: Q
Question
QUESTION 21
For bidding purposes, a _______________ is evaluated based upon area measured.
Fencing
Earthwork excavation
Sewer lines
None of the above
QUESTION 22
In general, it is recommended to permit the inspector to order the contractor to stop operations.
True
False
QUESTION 23
In federal agency projects, it is the inspector's responsibility to determine the specific needs of the types of construction records that must be established and maintained throughout the project.
True
False
QUESTION 24
In general, soil is classified as _______ grained if most of its sample weight passes the #200 sieve.
Fine
Medium
Smooth
Coarse
QUESTION 25
It is recommended that the inspectors assumes contractor' s possible mistakes rather than deliberate dishonesty and poor work.
True
False
QUESTION 26
It is possible to allow significant deviations from plans and specifications without a change order provided that no cost or time extension is involved.
True
False
QUESTION 27
It is acceptable to use the number of truckloads of loose material in determining earthwork volume.
True
False
QUESTION 28
According to OSHA, a cohesive soil is classified as type ____.
A
B
C
D
QUESTION 29
If the subcontractor allowed his/her crew to be exposed to hazards that could cause serious physical harm or death, who should be held liable for that?
The designer
The subcontractor
The General Contractor
Both of b and c
QUESTION 30
In federal contracts, a CQC representative is responsible for conducting all inspections.
True
False
Explanation / Answer
21. For bidding purposes, a earthwork excavation is evaluated based upon area measured. The area thus measured will be evaluated while determining the costs involved and hence the bidding.