Jack Simpson, contract negotiator for Nebula Airframe Company, is currently invo

ID: 461108 • Letter: J

Question

Jack Simpson, contract negotiator for Nebula Airframe Company, is currently involved in bidding on a follow-up government contract. In gathering cost data from the first three units, which Nebula produced under a research and development contract, he found that the first unit took 2,500 labor hours, the second took 1,875 labor hours, and the third took 1,760 hours. Use Exhibit 6.5. In a contract for three more units, how many labor hours should Simpson plan for? (Round your answer to the nearest whole number.)

Explanation / Answer

First Unit- 2500 Labor hours, The second unit-1875 Labor hours. The third unit- 1760 Labor hours The fourth unit-1470 Fifth Unit-1235 Sixt unit-956