The BOM for product A is shown below and data from the inventory records are sho
ID: 461209 • Letter: T
Question
The BOM for product A is shown below and data from the inventory records are shown in the table below. In the master production schedule for product A, the MPS start row calls for 150 units in week 3 and 100 in week 6.
Data Category B C D
Lot-sizing rule L4L FOQ = 300 POQ(P=3weeks)
Lead time 2 weeks 1 week 1 weeks
Scheduled receipts NONE 200(in week 3) 200(in week 3)
Beginning (on-hand) 50 200 0
inventory
MPS Product A
Week 1
2
3
4
5
6
Product A
Planned Order Release
Item C
Week
1
2
3
4
5
6
Gross Requirements
Scheduled Receipts
Projected OH inventory
Planned Order Receipts
Planned Order Releases
Item D
Week
1
2
3
4
5
6
Gross Requirements
Scheduled Receipts
Projected OH inventory 0
Planned Order Receipts
Planned Order Releases
Item B =
Week
1
2
3
4
5
6
Gross Requirements
Scheduled Receipts
Projected OH inventory 0
Planned Order Receipts
Planned Order Releases
Comment
MPS Product A
Week 1
2
3
4
5
6
Product A
Planned Order Release
Explanation / Answer
POR for Item is 150 units in week 3 and 100 units in week 6.
Now the calculation for item C
Given: L4L Tech. LT = 2 weeks, Sch Receipts = None and Inventory = 50 units, Using this information and BOM, the following table is drawn:
Now the calculation for item D,
Given: FOQ = 300, LT = 1week, SR = 200 in week 3 and Inv = 200
Now the calculations for item E,
Given: POQ (P = 3 weeks), LT = 1 week, SR = 200 (in week 3), inventory = 0
Week (Item C) 1 2 3 4 5 6 Gross Requirements 150 100 Sch. Receipts On Hand Inventory(50 units) 50 50 100 100 100 0 Planned Order Receipts Planned order Release 0 0 0 0 0 0Related Questions