QUESTION 17 Prior to coating application, evaluation of the surface preparation
ID: 463936 • Letter: Q
Question
QUESTION 17
Prior to coating application, evaluation of the surface preparation equipment includes the Following Except:
Compressor air cleanliness
Blast cleaning machine
Abrasive inspection
None of the above
QUESTION 18
Compensation for thermal expansion in buried plastic pipe can be achieved by snaking the line from side to side in the trench.
True
False
QUESTION 20
There is no joint sawing schedule that should be ideal for every job.
True
False
QUESTION 21
Sand should never be used as backfilling for pipeline installation.
True
False
QUESTION 22
In inspecting dry film thickness, we take the average of _____ gauge readings.
5
10
15
20
QUESTION 23
Air entrainment is used in concrete to:
Create a better surface appearance.
Increase the resistance of concrete to freeze-thaw effects.
Strengthen the concrete
Help evaporate excess water from the curing concrete.
QUESTION 24
The most common type of sheet piles is the ______ type.
Concrete
Wood
Steel
Cooper
QUESTION 25
The most important characteristic that the inspector should note about a concrete plant is the __________ of the mixes it produces.
strength
workability
grades
consistency
QUESTION 26
In a group of concrete samples, the strongest will be the one:
Cured underwater for a year
Moist-cured for 3 weeks, then allowed to air dry.
Moist-cured for 3 days, then allowed to air dry.
Cured in the air for a year.
QUESTION 27
Screeding (concrete leveling to proper elevation in the forms) takes place before consolidation.
True
False
QUESTION 28
Which of the following is a major concern when placing concrete:
Consolidation
Drop height
Distance moved after placed in for work.
All of the above.
QUESTION 29
Because of the reinforcement strength in concrete pipe, point load lifting and placement of pipe is not a concern for an inspector.
True
False
QUESTION 30
In reinforced concrete, it is acceptable to have light rust on the surface of the steel.
True
False
Explanation / Answer
Prior to coating application, evaluation of the surface preparation equipment includes the Following Except:
Abrasive inspection
QUESTION 18
Compensation for thermal expansion in buried plastic pipe can be achieved by snaking the line from side to side in the trench.
True
QUESTION 20
There is no joint sawing schedule that should be ideal for every job.
True
QUESTION 21
Sand should never be used as backfilling for pipeline installation.
False
QUESTION 22
In inspecting dry film thickness, we take the average of _____ gauge readings.
5
10
15
20
QUESTION 23
Air entrainment is used in concrete to:
Create a better surface appearance.
Increase the resistance of concrete to freeze-thaw effects.
Strengthen the concrete
Help evaporate excess water from the curing concrete.
QUESTION 24
The most common type of sheet piles is the ______ type.
Concrete
Wood
Steel
Cooper
QUESTION 25
The most important characteristic that the inspector should note about a concrete plant is the __________ of the mixes it produces.
strength
QUESTION 26
In a group of concrete samples, the strongest will be the one:
Moist-cured for 3 days, then allowed to air dry.
QUESTION 27
Screeding (concrete leveling to proper elevation in the forms) takes place before consolidation.
True
QUESTION 28
Which of the following is a major concern when placing concrete:
Consolidation
QUESTION 29
Because of the reinforcement strength in concrete pipe, point load lifting and placement of pipe is not a concern for an inspector.
False
QUESTION 30
In reinforced concrete, it is acceptable to have light rust on the surface of the steel.
True