The plant manager for the local electric utility company wants to determine the reliability of one of the small hydroelectric power generating systems. The system is comprised of two components: a generator which has a random failure rate of one in every two years of operation; and a transformer which has a random failure rate of one in every five years of operation.
1. If he were to add just a backup generator, what would be the probability that this system would perform reliably for a period of one year?
A. 0.48
B. 0.60
C. 0.72
D. 0.75
E. 0.96
Explanation / Answer
A. 0.48