In 1999, the XY Department of the Federal Government reviewed its Year 2000 Date
ID: 465534 • Letter: I
Question
In 1999, the XY Department of the Federal Government reviewed its Year 2000 Date Turnover Computer Risks and found that its outdated computer systems for managing public clients needed replacing. A business case was prepared for funding the replacement while at the same time implementing some improvements. The total budget requested was $2.3 million. In view of a shortage of funds around at the time, government did not approve this amount. Only $1.5 million was authorized. However, the XY Department accepted this amount after they decided that they could maybe do the work for around the $1.5M. Accordingly, a project was scoped and planned, with specific milestones for implementing the hardware and, subsequently the software, across 87 sites within its jurisdiction. A final completion date of 30th June 2001 was projected. The original business case had loosely identified some risks to the project that were also included in the project plan. A project steering committee was established, with the department chief (CEO) as the sponsor, and representation by influential managers with differing outcome needs to suit their particular work environment. The project commenced in July 1999. In view of the shortfall on its original budget request, the committee decided not to employ a project manager. Instead it assigned this responsibility to its Finance Manager, who would undertake the work along with his normal duties. A Company, called "Good Programs" was contracted to supply the software and assist in the implementation. This company recognized the marketing opportunities of this project, as the XY Department was its biggest client in the region. As a result, they offered, free of charge, many more features that were not in the original scope, provided the department allowed them to be, in essence a research and development (R&D) site. This would assist Good Programs to more readily sell their products elsewhere around the world, while providing the XY Department with additional functionality and benefits. Initially, the steering committee met regularly, but as new versions of the resulting software were being implemented regularly, meetings became less frequent and Good Programs were left to do more and more of the day to day management of the new version implementations. These new versions were developed after consultation with the various individual managers to accommodate requested new features with little consultation amongst all of the managers. All the XY Department and steering committee had to do was to identify problems with the software and to make the system testers available for new versions. However, the effect was an unanticipated overhead for the department. Sometime after the original project was scoped and commenced, both the original CEO and finance manager had been moved out of the department and new officers have been appointed. At this time, the new CEO has been advised that about $185,000 more is needed for the project, which is not in his current budget. The original project has not been signed off, indeed, it is evident that it has not been completed. The new CEO of the department is not sure of the original scope of the project, what aspects have been implemented, nor what has been spent for which parts. There do not seem to be any reliable reports available as to original scope, scope changes, schedule or budget. The CEO is concerned that the project has become more of a career than a project, with version 16.5 of the client management system now being tested with yet more features. In addition, there are some past software problems that are still outstanding. Nevertheless, Good Systems have promised that problems will be fixed in the next version… Questions You are a senior consultant with PM Right Track (PMRT), a competent project management consulting company. The CEO has called you in for advice. The information is brief, but this is all the information that he and the new finance manager are able to provide. The CEO's mandate to you is to: 1. Report your assessment of the current project status. 2. Compare your assessment with sound project management practices. 3. Recommend steps to bring the project to a close. 4. Recommend improvements to the XY Department's future project management practices. 5. If a very similar project had to be done again, what attributes and/or skill sets would you recommend in selecting a project manager? 6. What other advice might you give to the CEO? 7. What are the lessons learned?
Explanation / Answer
1. Current Project status: The project is partially implemented and most of the critical features are yet to be implemented. Those critical feature that has been implemented become over burden as those level of modification is not required. There is lack of requirement document and development team has no updated document that they refer. The development team is working on verbal discussion with few SME. The testing team is overburdened because of continuous arrival of build with major changes without any document. The mode of deployment of software at different sites is also not planned. The project budget has over-shoot, Quality is suffering because of lack of base document and scope keeps on changing as per SME.
2.
The project should have a project plan which can be shared among all the team so that they can prepare their respective plans and can align their milestone with project milestone. The requirement team should gather requirement and document it as a baseline document by taking final approval from department SME. The requirement document should be base for development team and testing team to design their process and task. There should be daily scheduled meeting within the team so that daily status and problem can be monitored and resolved. There will be weekly meeting by the senior management to understand the status of project implementation and major roadblocks.
3.
Analyze the current status of the project. Compare it with initial project plan. Identify the gaps. Create plan to fulfill those gaps. Daily monitoring of the project .Tailor the scope of project as per budget and implement it at critical site. Focus on required feature and its compatibility with existing applications.
Author's Note: Please be specific to the question that need to be answered.
7.
Lessons learned are:
Related Questions
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.