Here is a network with the activity times shown in days: Determine the critical

ID: 466684 • Letter: H

Question

Here is a network with the activity times shown in days: Determine the critical path. A-B-D-E-G A-C-D-E-G A-B-D-F-G A-C-D-F-G The following table shows the normal times and the crash times, along with the associated costs for each activity. If the project is to be shortened by four days, which activities, in order of reduction, would be shortened? (You may select more than one answer. Single click the box with the question mark to produce a check mark for a correct answer and double click the box with the question mark to empty the box for a wrong answer.) C, A (or E), F (or D) A, D, B, F E, A D, C (or E), F (or D) Find the resulting cost to crash. Resulting cost $

Explanation / Answer

option C is the crititcal path

b. option A is right

the cost will be increased by $2900

Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at
drjack9650@gmail.com
Chat Now And Get Quote