Problem 9-2 In the following MRP planning schedule for Item J, indicate the corr

ID: 468657 • Letter: P

Question

Problem 9-2 In the following MRP planning schedule for Item J, indicate the correct net requirements, planned order receipts, and planned order releases to meet the gross requirements. Lead time is one week. (Leave no cells blank - be certain to enter "O" wherever required.) WEEK NUMBER ITEM J Gross requiremen On-hand 2 70 4 45 65 30 et requirements Planned order receipt Planned order release Period 45 65 Gross requirements Scheduled receipts temJ Projected available balance 70 LT=1 Q=L4L Net requirements Planned order receipts Planned order releases

Explanation / Answer

Materials requirement plan (MRP) for J, lead time one weeks, Lot-for-Lot 1 2 3 4 5 Gross requirements 0 70 0 45 65 Schedule receipts 0 0 0 0 0 Projected available balance 0 0 0 0 0 Net requirements 70 0 45 65 Planned order receipts 70 0 45 65 Planned order releases 70 0 45 65 0

Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at
drjack9650@gmail.com
Chat Now And Get Quote