Advantage Energy Technology Data Center Migration Advantage Energy Technology is

ID: 469858 • Letter: A

Question

Advantage Energy Technology Data Center Migration Advantage Energy Technology is one of five national software companies that provide an accounting and business management package for oil jobbers and gasoline distributors. Recently, the company has decided to migrate its large data center to a new office location. The data center provides clients with remote access to a complete suite of application software system, and Advantage Energy Technology has held a previous competitive advantage in its industry due to its trademark reliability in regards to information technology (Larson, 2013). Migration Details. Brian Smith, the network administrator at Advantage Energy Technology, has been given the responsibility of implementing the migration, and has compiled the following data:

#

Task Name

Optimistic

Duration

Likely

Duration

Pessimistic

Duration

Immediate

Predecessor

Critical Path

1

AET DATA CENTER MIGRATION

54

68

92

-

-

2

Team Meeting

0.5

1

1.5

-

YES

3

Hire Contractors

6

7

8

2

-

4

Network Designs

12

14

16

2

-

5

Ventilate System

-

-

-

-

-

6

Order Ventilation System

18

21

30

2

-

7

Install Ventilation System

5

7

9

6

-

8

New Racks

-

-

-

-

-

9

Order New Racks

13

14

21

2

YES

10

Install Racks

17

21

25

9

YES

11

Power Supplies and Cables

-

-

-

-

-

12

Order Power Supplies & Cables

6

7

8

2

-

13

Install Power Supplies

5

5

11

12, 16

-

14

Install Cables

6

8

10

12, 16

YES

15

Renovation of Data Center

19

20

27

3, 4

-

16

City Inspection

1

2

3

3, 7, 10

YES

17

Switchover Meetings

-

-

-

-

-

18

Facilitates

7

8

9

14

-

19

Operations / Systems

5

7

9

14

-

20

Operations / Telecom

6

7

8

14

-

21

Systems and Applications

7

7

13

14

-

22

Customer Service

5

6

13

14

YES

23

Power Check

0.5

1

1.5

13, 14, 15

YES

24

Install Test Servers

5

7

9

18, 19, 20, 21, 22, 23

YES

25

Management Safety Check

1

2

3

7, 23, 24

YES

26

Primary Systems Check

1.5

2

2.5

25

YES

27

Set Date for Move

1

1

1

26

YES

28

Complete Move

1

2

3

27

YES

Based on these estimates and the resultant expected project duration of 69 days, the executive committee wants to know what is the probability of completing the project before a scheduled time (Ts) of 68 days?

Response 1. ANSWER NEEDED

The significance of this project has the executive committee very concerned. The committee has decided that more analysis of the duration of each activity is needed. Prior to conducting that effort, they have asked the network administrator to calculate what the expected project duration would have to be to ensure a 93 percent chance of completion within 68 days.

Response 2. ANSWER NEEDED

Accounts Payable System.

The sales department of Advantage Energy Technology has been concerned with a new start-up company that is about to release an accounts payable system. Investigation indicates that this new package will provide competitive features with products available at Advantage Energy Technology, and in some cases, exceeding current capabilities. The senior applications developer, Tom Wright, has been tasked with analyzing, designing, developing, and delivering a new accounts payable system for customers.

Complicating the issue of a new product release is the concern from the sales department relating to Advantage Energy Technology’s recent inability to meet promised delivery dates. The sales teams have convinced the company CEO that a significant marketing effort will have to be launched in order to convince customers that the new Advantage Energy Technology product will be worth the wait. Consequently, the following actions have been decided: estimating efforts of software developers will be tightened, use PERT techniques to generate probabilities associated with delivery dates, and incorporate new estimating procedures. Results of these actions can be viewed below:

#

Task Name

Optimistic

Duration

Likely

Duration

Pessimistic

Duration

Immediate

Predecessor

Critical Path

1

ACCOUNTS PAYABLE SYSTEM

-

-

-

-

-

2

Planning Meeting

1

1

2

-

YES

3

Team Assignments

3

4

5

2

YES

4

Program Specifications

-

-

-

-

5

Customer Requirements

8

10

12

3

YES

6

Feasibility Study

3

5

7

5

-

7

System Analysis

6

8

10

5

YES

8

Prelim Budget & Schedule

1

2

3

7

YES

9

Functional Specification

3

5

7

7

YES

10

Prelim Design

10

12

14

9

YES

11

Configuration & Perf Needs

3

4

5

10

YES

12

Hardware Requirements

4

6

8

11

YES

13

System Specifications

5

7

9

10

-

14

Detailed Design

12

14

16

12, 13

YES

15

Program Specifications

8

10

12

14

YES

16

Programming: First Phase

27

32

37

15

YES

17

Documentation

14

16

18

10

-

18

Prototype

-

-

-

-

19

Development

5

7

9

16

YES

20

User Testing & Feedback

12

14

16

19

YES

21

Programming: Second Phase

10

12

14

16

-

22

Beta Testing

18

20

22

21

-

23

Final Documentation Package

9

10

11

17, 20

YES

24

Training Package

4

5

6

21 SS, 23

YES

25

Product Release

3

5

7

22, 23, 24

YES

Based on these estimates and the critical path, the project duration is estimated at 149 days. But, a salesman at Advantage Energy Technology in the Southeastern Region has discovered that the competing accounts payable package is scheduled for delivery in 145 days. The sales force is very anxious to beat the delivery time of the competing product. The executive committee ask the senior applications developer for an estimated probability of reducing his expected project duration by two days.

Response 3. ANSWER NEEDED

The executive committee is advised by the senior applications developer that after all the estimating was completed, he determined that one of his two critical systems analysts might have to move out of the area for critical family reasons. The department is still very confident that the original delivery date of 149 days can be met with staffing rearrangements, assistance from subcontractors, and some senior level involvement.

This news is very disconcerting to the committee and the sales staff. At this point, the committee decide that based on the most recent delivery performance of Advantage Energy Technology, a modified, comfortable delivery date should be communicated to the customer clients. The senior applications developer is asked to calculate what the expected project duration would have to be to ensure a 98 percent chance of completion within 160 days so Advantage Energy Technology can publish and communicate such dates to clients.

Response 4. ANSWER NEEDED

#

Task Name

Optimistic

Duration

Likely

Duration

Pessimistic

Duration

Immediate

Predecessor

Critical Path

1

AET DATA CENTER MIGRATION

54

68

92

-

-

2

Team Meeting

0.5

1

1.5

-

YES

3

Hire Contractors

6

7

8

2

-

4

Network Designs

12

14

16

2

-

5

Ventilate System

-

-

-

-

-

6

Order Ventilation System

18

21

30

2

-

7

Install Ventilation System

5

7

9

6

-

8

New Racks

-

-

-

-

-

9

Order New Racks

13

14

21

2

YES

10

Install Racks

17

21

25

9

YES

11

Power Supplies and Cables

-

-

-

-

-

12

Order Power Supplies & Cables

6

7

8

2

-

13

Install Power Supplies

5

5

11

12, 16

-

14

Install Cables

6

8

10

12, 16

YES

15

Renovation of Data Center

19

20

27

3, 4

-

16

City Inspection

1

2

3

3, 7, 10

YES

17

Switchover Meetings

-

-

-

-

-

18

Facilitates

7

8

9

14

-

19

Operations / Systems

5

7

9

14

-

20

Operations / Telecom

6

7

8

14

-

21

Systems and Applications

7

7

13

14

-

22

Customer Service

5

6

13

14

YES

23

Power Check

0.5

1

1.5

13, 14, 15

YES

24

Install Test Servers

5

7

9

18, 19, 20, 21, 22, 23

YES

25

Management Safety Check

1

2

3

7, 23, 24

YES

26

Primary Systems Check

1.5

2

2.5

25

YES

27

Set Date for Move

1

1

1

26

YES

28

Complete Move

1

2

3

27

YES

Explanation / Answer

In order to find the probability of completing the project within 68 days, we have to calculate The Z value, I.e ., Converting the given question into standard Normal distribution

Z= (X-Mean)/ SD,

Where ,

X is 68 days ( We are going to find the proabbility of finishing the project within 68 days)

Mean is 69 Days, It is given in the question , the expected duration of completing is 69 days

SD, the standard deviation, which we have to calclulate

Where SD= Square root (Sum of each ((Tp-To)/6)2 ) in the critical path. ( Tp is the pessimistic time and To is the optimistic time)

The calcualtion is given below

Z= (X-Mean)/ SD,

Z= (68-69)/2.57

Z= -1/2.57 = -0.38910

The probability of finishing the job within 38 days is P(Z<-0.3891) =

= 0.5- Table value of Z from 0 to 0.3891

=0.5- 0.1517 = 0.3483

I.e . 34.83%

# Task Name Optimistic Likely Pessimistic Immediate Critical Path Standard Deviation Duration Duration Duration Predecessor 1 AET DATA CENTER MIGRATION 54 68 92 - - 2 Team Meeting 0.5 1 1.5 - YES 0.027777778 3 Hire Contractors 6 7 8 2 - 4 Network Designs 12 14 16 2 - 5 Ventilate System - - - - - 6 Order Ventilation System 18 21 30 2 - 7 Install Ventilation System 5 7 9 6 - 8 New Racks - - - - - 9 Order New Racks 13 14 21 2 YES 1.777777778 10 Install Racks 17 21 25 9 YES 1.777777778 11 Power Supplies and Cables - - - - - 12 Order Power Supplies & Cables 6 7 8 2 - 13 Install Power Supplies 5 5 11 12, 16 - 14 Install Cables 6 8 10 12, 16 YES 0.444444444 15 Renovation of Data Center 19 20 27 3, 4 - 16 City Inspection 1 2 3 3, 7, 10 YES 0.111111111 17 Switchover Meetings - - - - - 18 Facilitates 7 8 9 14 - 19 Operations / Systems 5 7 9 14 - 20 Operations / Telecom 6 7 8 14 - 21 Systems and Applications 7 7 13 14 - 22 Customer Service 5 6 13 14 YES 1.777777778 23 Power Check 0.5 1 1.5 13, 14, 15 YES 0.027777778 24 Install Test Servers 5 7 9 18, 19, 20, 21, 22, 23 YES 0.444444444 25 Management Safety Check 1 2 3 7, 23, 24 YES 0.111111111 26 Primary Systems Check 1.5 2 2.5 25 YES 0.027777778 27 Set Date for Move 1 1 1 26 YES 0 28 Complete Move 1 2 3 27 YES 0.111111111 Sum 6.638888889 SD 2.576604139