Young bulls contracting repaved 50 miles of two-lane roadway with a crew of six
ID: 471912 • Letter: Y
Question
Young bulls contracting repaved 50 miles of two-lane roadway with a crew of six employees. The crew worked eight days and used $7000 worth of paving materials. Nearby little dog construction repaved 30 miles of four-lane roadway working ten days with a crew of five people using $9000 of paving material. Both young bull and little dog rented the same paving equipment to complete their respective products costing each $1500 per day.
Young bull's labor productivity_________________ = single lane miles/ day (one decimal place)
little dog's labor productivity___________________ = single lane miles/day
Young bull's labor productivity =
Explanation / Answer
young bulls build 50 miles two lane road, it can be consider as 100 miles of single lane
the productivity= 100/64= 1.5625miles per day
little dogs productivity= 30*4= 120 miles single lanes/per one labor
the productivity= 120/50= 2.4 miles single lane per day/one labor