The following data is available for three different alternatives. Alternatives B
ID: 1166713 • Letter: T
Question
The following data is available for three different alternatives. Alternatives B and C are replaced at the end of their useful lives with identical replacements.
Using present worth analysis, find the best alternative. Please Show Work.
Alternative The following data is available for threeData different alternatives. Alternatives B and C are replaced at the end of their useful lives with identical replacements Using present worth analysis, find the best alternative. Initial Cost Uniform Annual S1,000 S1,500 S2,000 S200 S276.20 S654.80 -eful Life in years 110 Interest Rate 1290Explanation / Answer
The present worh for A is -1000+200(1/1.12+1/1.12^2+1/1.12^3+...)=667
The present worth for B is -1500+276.2(1/1.12+1/1.12^2+...+1/1.1^210)=60
The present worth for C is -2000+654.8(1/1.12+1/1.12^2+...1/1.12^5)=360
So, the project A is the most profitable.
Related Questions
Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at
drjack9650@gmail.com
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.