Engineering Economy class. Please, when answering this problem, it will be more than appreciated if you can present the whole process (equations) before solving. Just to understand better everything. Example: Present Value = 20,000(P/F, i, n)+45,000(A/F, i, n)(P/F, i, n)... Thanks in advance!

There are two manufacturing processes that can be used by a company to reduce energy losses in the equipment’s. The following cost information for these two processes is known:

By doing the following analysis, select which manufacturing process must be selected (A or B):

a) Find the Present Value with an interest rate of 12% annually computed quarterly.

b) Quarterly equivalent uniform value with an interest rate of 8% annually computed quarterly

c) Capitalized Cost with an interest rate of 14% annually computed quarterly

d) Which manufacturing process must be selected

Process A Process B Initial Cost $170,000 $220,000 Operation and Maintenance Cost $7,000 quarterly $5,000 quarterly Useful Life (Life Cycle) 2 years 4 years Residual Value $30,000 $42,000

Explanation / Answer

Solution :

a) The present value of cash flows with an interest rate of 12% annually computed quarterly.

PV = - $ 7000 / ( 1+(0.12/4))4X1+ - $ 7000 / ( 1+(0.12/4))4X2

PV = -$ 6219.40 - $ 5525.86

PV = -$ 11,745.26

Residual cash flows = $ 30,000

Present value of residual cash flow = $ 30,000 / ( 1+(0.12/4))4X2

Present value of residual cash flow = $ 23,682.27

Net present value = -$ 170,000 - -$ 11,745.26 + $ 23,682.27

Net present value = -$ 158,062.99