Academic Integrity: tutoring, explanations, and feedback — we don’t complete graded work or submit on a student’s behalf.

Question 2 (10 marks) You are in charge of building a new office for your compan

ID: 1214592 • Letter: Q

Question

Question 2 (10 marks)

You are in charge of building a new office for your company. After some discussion with your builder, you identified some of the key tasks, the duration and the costs to complete the building. As you are a project manager you have decided to monitor the building progress using Earned Value Management (EVN). Answer the following questions using the following information

ID

Task Name

Cost ($)

Start Date

Duration

1

Lay foundations

18,000

November 1

2 weeks

2

Build frame

34,000

November

4 weeks

3

Install pipes and electrical

10,000

December

6 weeks

4

Make office water-tight

15,000

February

8 weeks

5

Install internal walls and bathroom

20,000

April

12 weeks

6

Install cabinetries

14,000

July

4 weeks

7

Paint office

8,000

August

2 weeks

8

Install light fixtures and appliances

9,000

August

2 weeks

NOTE: Assume that no task is scheduled to run concurrently, e.g., Task 2 starts after Task 1 completes, Task 3 starts only when Task 2 completes, and so on. Also, assume that each month is made up of exactly four weeks.

What is the planned value of the entire project?

[1 mark]

The project manager has managed to keep cost to what was originally budgeted above. At this point, the project has completed Task 4. Up to this point,

What is the planned value of the project?

What is the actual cost (AC) of the project? Briefly explain how you derive the actual cost.

What is the rate of performance (RP) for each task? Using the RPs obtained, calculate the Earned Value (EV), Schedule Variance (SV), Cost Performance Index (CPI), and Schedule Performance Index (SPI) of the project.

[1 + 1 + 1 = 3 marks]

Unfortunately, two trades resigned after Task 5 was completed and this caused the remaining tasks to exceed its original cost and schedule by 25%, 30%, 40% respectively. At the end of the project,

What are the CPI and SPI?

How is the performance with respect to cost and time?

Represent the Planned Value (PV), Earned Value (EV) and Actual Cost (AC) in a chart

[1 + 1 + 4 = 6 marks]

ID

Task Name

Cost ($)

Start Date

Duration

1

Lay foundations

18,000

November 1

2 weeks

2

Build frame

34,000

November

4 weeks

3

Install pipes and electrical

10,000

December

6 weeks

4

Make office water-tight

15,000

February

8 weeks

5

Install internal walls and bathroom

20,000

April

12 weeks

6

Install cabinetries

14,000

July

4 weeks

7

Paint office

8,000

August

2 weeks

8

Install light fixtures and appliances

9,000

August

2 weeks

Explanation / Answer

Planned value= 128000

2) 77000(up to task 4)

3)Actual cost= 128000

4. Rate of performance= 102400/ 128000 x 100=8%

5. Rate of performance = 12% (approx.)

6. Earned value= 128000/8=16000

7. Variance = 9000 - 128000 / 9000 + 128000 = 0.8%

Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at
drjack9650@gmail.com
Chat Now And Get Quote