Two days afetr a planned reactor shutdonw from 100% power, maintenance is to per
ID: 1396498 • Letter: T
Question
Two days afetr a planned reactor shutdonw from 100% power, maintenance is to performed on one of two reactor primary heat exchangers, Each heat exchangers is rated at 12,000Btu/hr. To determine the current decay heat load, cooling is secured to both heat exchangers. The primary system heats up ar a rate of 1.8 degree F . The primary system contains 24,000 lb of coolant with a specific heat capacity of 0.8 Btu/lbm F. Will on heat exchanger be sufficient to remove the decay heat? Explain answer. Show all work
Explanation / Answer
decay heat = Q = mc dT/dt
here m for primary system = 24,000 lb
dT/dt = 1.8 degree F / hr
c = specific heat capacity = 0.8 Btu/lbm F
Q = 24000 * 1.8 x 0.8
Q = 34,560 Btu/hr
Each heat exchangers is rated at 12,000Btu/hr
hre Q = 34,560 Btu/hr
so one heat exchanger will not be sufficient