A preconstruction conference should be he held: A. during the bid phases B. afte
ID: 1709788 • Letter: A
Question
A preconstruction conference should be he held: A. during the bid phases B. after agreement but before notice to proceed C. prior to advertising for bids D. after bid opening but after award of the contract E. after Notice to Proceed. A resident project representative should be aware of project safety and if he or she observes a hazardous condition while inspecting the Work, the first thing he or she should do is: A. ignore the unsafe condition for it is beyond his or her authority. B. have the unsafe condition for it is beyond his or her own authority. C. notify the Building Department of the unsafe condition. E. order any workers to move out of the hazardous area. The main purpose of construction inspection is to: A. assure top quality materials and workmanship. B. detect dishonesty or incompetence. C. enforce building codes. D. assure compliance with contract documents. E. police the job. A sub-contractor reports that the approved material is no longer in production. The subcontractor then brings in data claiming the superiority of a new substitute product. The resident project representative should: A. approve the changes and carefully file the data. B. ask the owner if it will be acceptable. C. leave the decision to the design engineer of record. D. refer the decision to the Superintendent. E. refer the matter to the construction manager Which of the following listed tasks it not recommended to be performed by the arch or engineer: A. verification of monthly pay quantities. B. assist in bid review and evaluation. C. recommend to the contractor the method of performing the work. D. documentation of construction activities. E. review shop drawings.Explanation / Answer
8) Option B
The preconstruction conference is typically scheduled after the contract has been signed, and shortly before ground breaking
9) Option E
If there is unsafe condition the work is not allowed to proceed.
10) Option D
Inspection of the construction works is carried out to verify compliance with the requirements of the contract documents.
Related Questions
Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at
drjack9650@gmail.com
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.