Academic Integrity: tutoring, explanations, and feedback — we don’t complete graded work or submit on a student’s behalf.

Question 31 1 pts Why does SPI sometimes behave weirdly in the latter periods of

ID: 1866916 • Letter: Q

Question

Question 31 1 pts Why does SPI sometimes behave weirdly in the latter periods of a project SPI must by definition equal 1.0 at the end of the project. SPI does not behave weirdly in the latter periods of a project None of the above Fewer work activities require completion later in a project The cost per unit of time decreases toward the end of a project Question 32 1 pts A learning curve reflects what? The beneficial effect of high market share Increases in productivity with cumulative duration of a project The effect of training on project team expertise None of the above Question 33 1 pts What is the purpose of a Control Account? To assign financial resources To control a project's progress To define responsibilities for work packages To structure the logic of the worlk

Explanation / Answer

31. SPI always limited to 1 when project was delayed.

So option a is correct.

32. A learning curve is a graphical representation of cumulative volume of production Vs average time per unit.

So option b is correct.

33. Control account helps in controlling the project progress.

Therefore option b is correct.

34

True.

As per Chegg rule first 4 subparts has to be answered

Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at
drjack9650@gmail.com
Chat Now And Get Quote