Consider the filming of the scene described in Problem 2. Based on past experien
ID: 1920391 • Letter: C
Question
Consider the filming of the scene described in Problem 2. Based on past experience, the director is not very confident about the time estimates for some of the activities. His estimates for the minimum, most likely, and maximum times for these activities are Including these PERT time estimates, how long is the filming expected to take? What is the probability that the filming is completed before 16 days? Before 24 days? How many days are required to complete the filming with probability 0.95? What is the probability that the number of days required to complete the filming of the scene is at least 30 percent larger than the answer you found in part (a)?Explanation / Answer
Before we start
Now coming to questions
Q1)
The expected time = (time of the critical path A-B-C-F-I-J-K) = 2+4.5 +1.0 +most likely(F-I-J-K)=22.17 days
Q2) P(completed before 16 days)=P(1-(16-22.17)/6.5)=1-0.8264 =0.1736=17.3%
P(completed before 24 days)=P((24-22.17)/6.5)=0.6103 =61.03%
Q3)P(z-22.17)/6.5)=0.95 thus Z=22.17+6.5*1.645=32.86 = approx 33 days
Q4) Z=130/100*22.17=28.82 days
P((28.82-22.17)/6.5)=0.842 = 84.2 %
note P here represents probability for normal distribution
Activity optimistic average pessimistic E(activity)=(a+4m+b)/6 Var(activity)=(b-a)^2/36 F 2 3 12 4.33 2.78 I 1 2 8 2.83 1.36 J 3 4 10 4.83 1.36 K 1 2 7 2.67 1.00 Most likely 14.67 Standard deviation 6.50Related Questions
Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at
drjack9650@gmail.com
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.