Contrasting ABC and Conventional Product Costs Rocky Mountain Corporation makes
ID: 2329732 • Letter: C
Question
Contrasting ABC and Conventional Product Costs
Rocky Mountain Corporation makes two types of hiking boots—Xactive and Pathbreaker, Data concerning these two product lines appear below:
Xactive
Pathbreaker
Direct materials per unit
$64.80
$51.00
Direct labor costs per unit
$18.20
$13.00
Direct labor -hours per unit
1.4 DLHs
1.0 DLHs
Estimated annual production and sales
25,000 units
75,000 units
The company has a conventional costing system in which manufacturing overhead is applied to units based on direct labor-hours. Data concerning manufacturing overhead and direct labor-hours for the upcoming year appear below:
Estimated total manufacturing overhead_____________$2,200,000
Required:
1.Compute the predetermined overhead rate based on direct labor-hours. Using this rate and other data from the problem, determine the unit product cost of each product.
2.The company is considering replacing its conventional costing system with an activity-based costing system that would assign its manufacturing overhead to the following four activity cost pools
Expected activity_____
Estimated
Activities and activity Measures Overhead Cost Xactive Pathbreaker Total
Supporting direct labor (direct $797,500 36,000 75,000 110,000
Labor -hours)
Batch setups(setups) 680,000 250 150 400
Product sustaining (number of
Products) 650,000 1 1 2
General Factory (machine-hours) 72,000 2,500 7,500 10,000
Total Manufacturing overhead
Cost $2,200,000
Xactive
Pathbreaker
Direct materials per unit
$64.80
$51.00
Direct labor costs per unit
$18.20
$13.00
Direct labor -hours per unit
1.4 DLHs
1.0 DLHs
Estimated annual production and sales
25,000 units
75,000 units
Explanation / Answer
1) Predetermined Overhead Rate ;-
= Estimated total manufacturing Overhead cost / Estimated total direct labor hours
= $2200000 / 110000 h
= $20 per hour
Estimated Total Direct Labor Hours :-
= (25000 units * 1.4 h per unit) + (75000 units * 1 h per unit)
= 35000 h + 75000 h
= 110000 hours
2) Total Manufacturing Overhead Cost :-
Activities and Activity Measures Cost Driver Estimated Overhead Cost ($) Expected Activity Acticity Rate Supporting direct labor (Direct Labor Hours) Direct Labor Hours 797500 110000 $7.25 per Labor Hour Batch Setup Set ups 680000 400 $1700 Per Set Up Product Sustaining No. of Products 650000 2 $325000 Per Product General Factory Machine hours 72500 10000 $7.25 Per Machine HourRelated Questions
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.