Academic Integrity: tutoring, explanations, and feedback — we don’t complete graded work or submit on a student’s behalf.

Exercise 17-1 (Part Level Submission) Standard Custom (a) Open Show Work SHOW SO

ID: 2338601 • Letter: E

Question

Exercise 17-1 (Part Level Submission)

Standard

Custom

(a)

Open Show Work

SHOW SOLUTION

LINK TO TEXT

LINK TO TEXT

(b)

Open Show Work

LINK TO TEXT

LINK TO TEXT

SAVE FOR LATER

SUBMIT ANSWER

(c)

The parts of this question must be completed in order. This part will be available when you complete the part above.

Exercise 17-1 (Part Level Submission)

Saddle Inc. has two types of handbags: standard and custom. The controller has decided to use a plantwide overhead rate based on direct labor costs. The president has heard of activity-based costing and wants to see how the results would differ if this system were used. Two activity cost pools were developed: machining and machine setup. Presented below is information related to the company’s operations.

Standard

Custom

Direct labor costs $52,000 $120,000 Machine hours 1,170 1,100 Setup hours 99 420
Total estimated overhead costs are $301,000. Overhead cost allocated to the machining activity cost pool is $197,000, and $104,000 is allocated to the machine setup activity cost pool.

(a)

Your answer is correct. Compute the overhead rate using the traditional (plantwide) approach. (Round answer to 2 decimal places, e.g. 12.25.)
Predetermined overhead rate

% of direct labor cost Click if you would like to Show Work for this question:

Open Show Work

SHOW SOLUTION

LINK TO TEXT

LINK TO TEXT

Attempts: 1 of 5 used

(b)

Compute the overhead rates using the activity-based costing approach. (Round answers to 2 decimal places, e.g. 12.25.)
Machining $

per machine hour Machine setup $

per setup hour Click if you would like to Show Work for this question:

Open Show Work

LINK TO TEXT

LINK TO TEXT

Attempts: 0 of 5 used

SAVE FOR LATER

SUBMIT ANSWER

(c)

The parts of this question must be completed in order. This part will be available when you complete the part above.

Explanation / Answer

a) Predetermined overhead rate= total estimed overhead cost/total direct labor cost 301,000 /(52000+120000) 175% of direct labor cost b) overhead rates using activity based costing approach Machining 197,000/(1170+1100) 86.78 Machine setup 104,000/(99+420) 200.39 Machining 86.78 per machine hour Machine setup 200.39 per setup hour

Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at
drjack9650@gmail.com
Chat Now And Get Quote