Academic Integrity: tutoring, explanations, and feedback — we don’t complete graded work or submit on a student’s behalf.

The following scenario will be used for the next three questions Miser Construct

ID: 2338611 • Letter: T

Question

The following scenario will be used for the next three questions Miser Construction Company (who applies the Percentage of Completion method) was the low bidder on a construction project to build a bridge for $14,000,000. The project was begun in 2016 and completed in 2018. Cost and other data are presented below ("costs incurred" are for each particular year): 2016 2017 2018 Costs incurred (during specific year) Estimated costs to complete (end of year) Billings during the year $3,0.000 $6,000,000 $2.800,000 $9,000,000 $3,000,000 $6,800,000 $6,600,000 $0 54,000,000 $4,600,000 $3,200,000 Cash collections during the year $%2,800,000

Explanation / Answer

Gross profit to be recognized under the percentage of completion method = (costs to date/total estimated costs*expected profits) - previously recognized profits

Costs to date = $3,000,000

Total estimated costs = Costs to date + Estimated costs to complete at the year end

= $3,000,000 + $9,000,000

= $12,000,000

Expected profits = Contract price - Total estimated costs

= $14,000,000 - $12,000,000

= $2,000,000

Previously recognized profits = $0

Profit to be recognized in 2016 = ($300,000/$12,000,000*$2,000,000) - $0

= $500,000

Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at
drjack9650@gmail.com
Chat Now And Get Quote