Academic Integrity: tutoring, explanations, and feedback — we don’t complete graded work or submit on a student’s behalf.

The following data is given for the Bahia Company: Budgeted production 1,077 uni

ID: 2343754 • Letter: T

Question

The following data is given for the Bahia Company:
Budgeted production
1,077 units
Actual production
959 units
Materials:

Standard price per pound
$1.81
Standard pounds per completed unit
12
Actual pounds purchased and used in production
11,163
Actual price paid for materials
$22,884
Labor:

Standard hourly labor rate
$15.00 per hour
Standard hours allowed per completed unit
4.0
Actual labor hours worked
4,938.85
Actual total labor costs
$75,317
Overhead:

Actual and budgeted fixed overhead
$1,125,010
Standard variable overhead rate
$28.00 per standard labor hour
Actual variable overhead costs
$138,288
Overhead is applied on standard labor hours.


Determine the factory overhead volume variance.

Explanation / Answer

[Factory overhead volume variance = Budgeted allowance based on standard hours allowed – Overhead charged to production]

Total Variable factory overhead / Direct labor hours

= $138,288 / 4,938.85 =28$

= $28.0 variable factory overhead rate

Total fixed factory overhead / Direct labor hours

= $22,884 / 4,938.85

= $4.63 fixed factory overhead rate

Total factory overhead rate at actual.

($28 + $4.63) = $32.63

actual cost = $32.63*4938.85=$161154

Budgeted

Total Variable factory overhead / Direct labor hours

= $15 variable factory overhead rate

Total fixed factory overhead / Direct labor hours

= $23392.44 / 4038

= $5.79 fixed factory overhead rate

Total factory overhead rate at actual.

($15+$5.79) = $20.79

Budgeted cost = 20.79*4038 =$83950.02

hence the

over head volume variance = 83950.02 - 161154 = (-$77204) unfavourable






Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at
drjack9650@gmail.com
Chat Now And Get Quote