Provence Bicycle Company manufactures road bikes. The following data for Septemb
ID: 2352764 • Letter: P
Question
Provence Bicycle Company manufactures road bikes. The following data for September of the current year are available:Quantity of direct Labor used: 650 hrs
Actual rate for direct labor: $14/hr
Bicycles completed in September: 280
Standard direct labor per bicycle: 2.25 hrs
standard rate for direct labor: $14.20/hr
a. Determine the direct labor rate variance and direct labor time variance. Use the minus sign to enter favorable variances as negative numbers.
Rate variance:$
Time variance:$
Total direct labor cost variance:$
b. How much direct labor should be debited to Work in Process?$
Explanation / Answer
a. Determine the direct labor rate variance and direct labor time variance. Use the minus sign to enter favorable variances as negative numbers. Rate variance = AH(AR-SR) = 650*(14 – 14.20) = -130, which is 130 favorable Time variance = SR(AH-SH) =14.20*(650 – 280*2.25) = 14.20*(650 – 630) = 284, which is 284 unfavorable Total direct labor cost variance = -130 + 284 = 154, which is 154 unfavorable b. How much direct labor should be debited to Work in Process?$ 650*14 = $9100 is debited to work in process
Related Questions
Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at
drjack9650@gmail.com
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.