On 5/1/14 Lavender Construction Co. entered into a fixed-price contract to const
ID: 2358025 • Letter: O
Question
On 5/1/14 Lavender Construction Co. entered into a fixed-price contract to construct an apartment building for $3,000,000. Lavender appropriately accounts for this contract under the percentage-of-complete method. Information relating to the contract is as follows: At 12/31/14 = 20% Complete / $2,250,000 estimated cost at completion / $150,000 Income recognized (cumulative). At 12/31/15 = 60% complete / $2,400,000 estimated costs at completion / $360,000 Income recognized (cumulative) / What is the amount of contract costs incurred during the year ended 12/31/15? (a) $600,000 (b) $960,000 (c) $990,000 (d) $1,440,000Explanation / Answer
(b) $960,000
Related Questions
Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at
drjack9650@gmail.com
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.