6. Suppose the standard for a given cost during a period was $80,000. The actual

ID: 2361686 • Letter: 6

Question

6. Suppose the standard for a given cost during a period was $80,000. The actual cost for the period was $72,000. Under what circumstances would you consider the variance from budget to be a positive performance indication? Question 6 options: A. The cost is fixed, and actual production was 90 percent of the standard level of budgeted production. B. The cost is variable, and the standard cost noted above is the cost at a production level lower than the actual production level. C. The cost is variable, and actual production was 90 percent of the standard level of production. D. The cost is variable, and actual production was 75 percent of the standard level of production.

Explanation / Answer

C. The cost is variable, and actual production was 90 percent of the standard level of production.

Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at
drjack9650@gmail.com
Chat Now And Get Quote