Calculate lead time Michigan Machining Company machines metal parts for the auto

ID: 2362751 • Letter: C

Question

Calculate lead time Michigan Machining Company machines metal parts for the automotive industry. Under the traditional manufacturing approach, the parts are machined through two processes: milling and finishing. Parts are produced in batch sizes of 60 parts. A part requires 5 minutes in milling and 7 minutes in finishing. The move time between the two operations for a complete batch is 10 minutes. Under the just-in-time philosophy, the part is produced in a cell that includes both the milling and finishing operations. The operating time is unchanged; however, the batch size is reduced to 5 parts and the move time is eliminated. Determine the value-added, non-value-added, total lead time, and the value-added ratio under the traditional and just-in-time manufacturing methods. If required, round percentages to one decimal place. Traditional Philosophy Just-in-Time Philosophy Value-added time min min Non-value-added time min min Total lead time min min Value-added ratio (as a percent) % %

Explanation / Answer

Just in time Lead time=60*(5+7)=720min Non-value-added time=720+(60*10)=720+600=1320min value added time=720+(55*10)=1270 value added ratio=1320/1270=103.93%

Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at
drjack9650@gmail.com
Chat Now And Get Quote