From the following information, develop an AON project network. Complete the for
ID: 2370097 • Letter: F
Question
From the following information, develop an AON project network. Complete the forward and backward pass, compute activity slack, and identify the critical path. How many days will the project take? Attach or insert your AON network. You may use MSP to check your work, but your submitted file should be similar to that shown in figure 6.8 of Larson & Gray.
ID
Description
Predecessor
Time (days)
A
Survey site
None
2
B
Install drainage
A
5
C
Install power lines
A
3
D
Excavate site
B, C
4
E
Pour foundation
D
3
ID
Description
Predecessor
Time (days)
A
Survey site
None
2
B
Install drainage
A
5
C
Install power lines
A
3
D
Excavate site
B, C
4
E
Pour foundation
D
3
Explanation / Answer
It will take 14 days to finish the project. There is a slack of 2 days.