Actual production during October was 53,000 bars and actual direct labor cost wa
ID: 2371093 • Letter: A
Question
Actual production during October was 53,000 bars and actual direct labor cost was $39,000.
Required:
Prepare a flexible budget for Ershey's Chocolates that shows the projected direct labor cost. If an amount is zero, enter "0".
What is the difference between the flexible budget and the actual labor costs?
Were the company's labor costs over or under budget for the month?
SelectOver budgetUnder budget
Explanation / Answer
Estimated production (bars) 53,000 bars
Direct labor per box 3 mins
Direct labor hours needed = 53,000*3/60 =2650 hrs
Direct labor cost per hour $15
Projected direct labor cost 2650*15 =$39750
difference between the flexible budget and the actual labor costs =39750-39000= $750
Over budget