Conceptual Connection: What is the payback period for each of Kambry Day\'s proj

ID: 2377071 • Letter: C

Question

Conceptual Connection: What is the payback period for each of Kambry Day's projects? Round your answers to two decimal places.

Project A years Project B years Kambry Day is considering investing in one of the following two projects. Either project will require an investment of $20,000. The expected cash flows for the two projects follow. Assume that each project is depreciable. Conceptual Connection: What is the payback period for each of Kambry Day's projects? Round your answers to two decimal places.

Explanation / Answer

project A


20000 - 6000


14000 - 8000


6000/10000


payback period = 2.6 years


priject B


20000 - 6000


14000 - 8000


payback period = 2.6 years