A company usesan activity based overhead allocation system, with three cost pools and drivers. Budgeted costs and drivers information for 2013 are as follows:
Cost pool 1 Cost pool 2 Cost pool 3
Budgeted Costs 103,000 57,000 31,000
Cost Drivers
Total 156,400 114,900 122,800
Job A 83,300 63,700 76,900
How much overhead was allocated to Job A?
Explanation / Answer
overhead allocated to job A = 103000*83300/156400
=54858.70