Calculate the earliest finish for Task D if one of its predecessors, Task A, fin

ID: 2379718 • Letter: C

Question

Calculate the earliest finish for Task D if one of its predecessors, Task A, finishes on day 3, its other predecessor, Task C, finishes on day 4, and the duration of Task D is 2 days. Question 25 options: A) day 6 B) day 3 C) day 4
D) Cannot be calculated based upon information given.


Calculate the latest start for Task B if its predecessor, Task A, finishes on day 3, its succeeding activity, Task E, has a latest start of day 7, and the duration of Task B is 2 days. Question 26 options: A) day 5 B) day 3 C) day 7 D) Cannot be calculated based upon information given.
The total completion time is 25 days. Task A is planned to take seven days. Task B is planned to take five days. Task C is planned to take eight days. The tasks have a serial relationship. How much slack does the project have? Question 28 options: A) Negative 5 days slack. B) Positive 5 days slack. C) Positive 17 days slack. D) Positive 3 days slack. Calculate the earliest finish for Task D if one of its predecessors, Task A, finishes on day 3, its other predecessor, Task C, finishes on day 4, and the duration of Task D is 2 days. Calculate the earliest finish for Task D if one of its predecessors, Task A, finishes on day 3, its other predecessor, Task C, finishes on day 4, and the duration of Task D is 2 days. A) day 6 B) day 3 C) day 4
D) Cannot be calculated based upon information given.


Calculate the latest start for Task B if its predecessor, Task A, finishes on day 3, its succeeding activity, Task E, has a latest start of day 7, and the duration of Task B is 2 days. Question 26 options: A) day 5 B) day 3 C) day 7 D) Cannot be calculated based upon information given.
The total completion time is 25 days. Task A is planned to take seven days. Task B is planned to take five days. Task C is planned to take eight days. The tasks have a serial relationship. How much slack does the project have? Question 28 options: A) Negative 5 days slack. B) Positive 5 days slack. C) Positive 17 days slack. D) Positive 3 days slack. A) day 6 B) day 3 C) day 4 D) Cannot be calculated based upon information given.


Calculate the latest start for Task B if its predecessor, Task A, finishes on day 3, its succeeding activity, Task E, has a latest start of day 7, and the duration of Task B is 2 days. Question 26 options: A) day 5 B) day 3 C) day 7 D) Cannot be calculated based upon information given.
The total completion time is 25 days. Task A is planned to take seven days. Task B is planned to take five days. Task C is planned to take eight days. The tasks have a serial relationship. How much slack does the project have? Question 28 options: A) Negative 5 days slack. B) Positive 5 days slack. C) Positive 17 days slack. D) Positive 3 days slack. Calculate the latest start for Task B if its predecessor, Task A, finishes on day 3, its succeeding activity, Task E, has a latest start of day 7, and the duration of Task B is 2 days. Question 26 options: A) day 5 B) day 3 C) day 7 D) Cannot be calculated based upon information given. Calculate the latest start for Task B if its predecessor, Task A, finishes on day 3, its succeeding activity, Task E, has a latest start of day 7, and the duration of Task B is 2 days. Calculate the latest start for Task B if its predecessor, Task A, finishes on day 3, its succeeding activity, Task E, has a latest start of day 7, and the duration of Task B is 2 days. A) day 5 B) day 3 C) day 7 D) Cannot be calculated based upon information given. A) day 5 B) day 3 C) day 7 D) Cannot be calculated based upon information given. The total completion time is 25 days. Task A is planned to take seven days. Task B is planned to take five days. Task C is planned to take eight days. The tasks have a serial relationship. How much slack does the project have? The total completion time is 25 days. Task A is planned to take seven days. Task B is planned to take five days. Task C is planned to take eight days. The tasks have a serial relationship. How much slack does the project have? A) Negative 5 days slack. B) Positive 5 days slack. C) Positive 17 days slack. D) Positive 3 days slack. A) Negative 5 days slack. B) Positive 5 days slack. C) Positive 17 days slack. D) Positive 3 days slack. A) day 6 B) day 3 C) day 4
D) Cannot be calculated based upon information given.


Calculate the latest start for Task B if its predecessor, Task A, finishes on day 3, its succeeding activity, Task E, has a latest start of day 7, and the duration of Task B is 2 days. Question 26 options: A) day 5 B) day 3 C) day 7 D) Cannot be calculated based upon information given.
The total completion time is 25 days. Task A is planned to take seven days. Task B is planned to take five days. Task C is planned to take eight days. The tasks have a serial relationship. How much slack does the project have? Question 28 options: A) Negative 5 days slack. B) Positive 5 days slack. C) Positive 17 days slack. D) Positive 3 days slack.

Explanation / Answer

1

2

3

C) day 4