4. Use the information in partially completed Table 1. What is the projected on-
ID: 2396887 • Letter: 4
Question
4. Use the information in partially completed Table 1. What is the projected on-hand inventory in week 5? A) 0 units B) 35 units C) 40 units D) 75 units 5. Use the information in partially completed Table 1. What is the MPS start quantity in week 2? A) 0 units B) 20 units C) 40 units D) 80 units 6. Use the information in partially completed Table 1. What is the available-to-promise (ATP) inventory in week 5? A) 0 units B) 35 units C) 53 units D) 80 units
Table 1 Item B Order Policy: 80 units Lead Time: 1 week Week 4 7 35 5 Quantity on Hand 601 Forecast Customer orders (booked) 60 20 Projected on Hand MPS quantit MPS start Available-to-promise 2 40 3 40 15 5 40 6 40 8 35 50 40 45 12 4. Use the information in partially completed Table 1. What is the projected on-hand inventory in week 5? A) 0 units B) 35 units C) 40 units D) 75 units 5. Use the information in partially completed Table 1. What is the MPS start quantity in week 2? A) 0 units B) 20 units C) 40 units D) 80 units 6. Use the information in partially completed Table 1. What is the available-to-promise (ATP) inventory in week 5? A) 0 units B) 35 units C) 53 units D) 80 unitsExplanation / Answer
Quantity on Hand = 60
Order Policy = 80 units
5) Option A. Projected in Hand Inventory in week 5 will be = 40-40 = 0 units
6) Option A. MPS Start quantity in week 1 is 80, and week 2 it will be 0.
7) Option D. ATP inventory in week 5 is 80-0 = 80 units.
Related Questions
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.