Academic Integrity: tutoring, explanations, and feedback — we don’t complete graded work or submit on a student’s behalf.

please solve the following 4 1 Question Three (a) The following Engineering Work

ID: 2397399 • Letter: P

Question

please solve the following

4 1 Question Three (a) The following Engineering Works activities are used in the manufacturing process of Sinatra a Cost Pools Activity Costs Machine Setup Materials Handling Inspection Cost Drivers Driver Consumption 40,000 number of setups 150 setups 120,000 pounds of materials 30,000 pounds 10,000sample size 100 units Required: The overhead rate for each activity above (b) The following activity usage were incurred in the production of Produ Usage 10 setups 3,000 pounds Activity Machine setup Materials handling Inspection Required: Total overhead costs for the production of Product Xing

Explanation / Answer

Q3) a) overhead rate for each activity Activity overhead Cost pools costs rate Machine setup 40,000/150 267 per setup Materials handling 120,000/30,000 4 per pound inspection 10,000/100 1000 per unit b) total overhead cost overhead Cost pools cost Machine setup 267*10 2670 Materials handling 4*3000 12000 inspection 1000*5 5,000 total overhead cost 19670 answer