Chan Company identified the following activities, costs, and activity drivers for 2017. The company manufactures two types of go-karts fast and standard. Activity Expected Costs Expected Activity $625,000100,000 parts Handling materials Inspecting produet Processing purchase orders Paying suppliers Insuring the factory Designing packaging 900,000 105,000 175,000 0,000 5,000 1,500 batches 700 orders 500 invoices 40,000 square feet 2 models 30 based on 100,000 budgeted direct labor 1. Compute a single plantwide overhead rate assuming that the company assigns overhead hours. 2. In January 2017 the fast model required 2,500 direct labor hours and the standard model required 6,000 direct labor hours. Assign overhead costs to each model using the single plantwide overhead rate Complete this question by entering your answers in the tabs below Required 1Required 2 Compute a single plantwide overhead rate assuming that the company assigns overhead based on 100,000 budgeted direct labor hours Required 2>

Explanation / Answer

Given, overhead activities

costs($)

Handling materials

625000

inspecting product

900000

processing purchase orders

105000

paying supplies

175000

insuring the factory

300000

designing packaging

75000

Total overhead costs

   2,180,000.00

1 ans

Under single plant wide overhead rate

A

Given, budgeted direct labour hours

       100,000.00

B

Total overhead costs

   2,180,000.00

Overhead rate per hour=B/A

21.8

2 Ans

given, Direct labour hours

fast model

2500

standard model

6000

A

Total direct labour hours

8500

B

Total overhead costs

   2,180,000.00

Overhead rate per hour=B/A

256.47

Total Direct labour hours required

Plantwide OH rate

Total overhead cost

FAST Model

2500

256.47

641175

standard model

6000

256.47

1538820

Total

2179995

Given, overhead activities

costs($)

Handling materials

625000

inspecting product

900000

processing purchase orders

105000

paying supplies

175000

insuring the factory

300000

designing packaging

75000

Total overhead costs

   2,180,000.00