Chan Company identified the following activities, costs, and activity drivers. T
ID: 2500405 • Letter: C
Question
Chan Company identified the following activities, costs, and activity drivers. The company manufactures two types of go-karts: Fast and Standard. Production volume is 10,000 units of the Fast model and 30,000 units of the Standard model. Compute a single plantwide overhead rate assuming that the company assigns overhead based on 100.000 budgeted direct labor hours. Assign overhead costs to each model assuming the Fast model requires 25,000 direct labor hours and the Standard model requires 60,000 direct labor hours. What is the overhead cost per unit for each model?Explanation / Answer
Chan Company Activity Cost $ Handling Materials 625,000.00 Inspecting products 900,000.00 Processing Pos 105,000.00 Paying suppliers 175,000.00 Insuring factory 300,000.00 Designing Packaging 375,000.00 Total Overhead costs 2,480,000.00 Budgeted Direct Labor Hrs 100,000.00 1 Plant wise Overhead rate per Direct Labor hour $ 24.80 2 Model Total DL Hrs requierd Plantwide OH rate Total OH cost Units produced OH cost per unit Fast Model 25,000.00 24.80 620,000 10,000 62.00 Standard Model 60,000.00 24.80 1,488,000 30,000 49.60
Related Questions
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.