The difference between the Actual cost and the Standard cost for direct labor is
ID: 2410054 • Letter: T
Question
The difference between the Actual cost and the Standard cost for direct labor is called:
Select one:
A. Direct Labor Rate Variance
B. Direct Labor Efficiency Variance
C. Direct Labor Split Variance
D. Direct Labor Flexible Budget Variance
E. None of the above
part 2
The difference between the split cost and the actual cost for direct materials is called the:
Select one:
A. Materials Price Variance
B. Materials Efficiency Variance
C. Materials Usage Variance
D. Materials Budget Variance
E. None of the above
Explanation / Answer
Answers
Correct Answer: D. Direct Labor Flexible Budget Variance
Standard cost is calculated for actual units as Actual Units x Standard hours x Standard rate. This Standard cost is also cost used in Flexible Budget.
Correct Answer: E. None of the above
A. Materials Price Variance – wrong because it’s based on the difference between standard price and actual price.
B. Materials Efficiency Variance – wrong because its based on difference between standard quantity and actual quantity.
C. Materials Usage Variance - wrong because its based on difference between standard quantity and actual quantity.