Using the abbreviations listed below, indicate for each of the costs whether the
ID: 2425674 • Letter: U
Question
Using the abbreviations listed below, indicate for each of the costs whether the cost should be classified as:(be sure to label each clearly) P = Prevention D = Detection I = Internal Failure E = External Failure N = none of the above 1. Inspecting products and processes 2. Verifying supplier environmental performance 3. Testing for contamination 4. Obtaining ISO 14001 certification 5. Carrying out environmental studies 6. Operating pollution control equipment 7. Cleaning up a polluted lake 8. Recycling scrap 9. Recycling products 10. Cleaning up oil spills
Explanation / Answer
Answer:
D 1. Inspecting products and processes
D 2. Verifying supplier environmental performance
D 3. Testing for contamination
P 4. Obtaining ISO 14001 certification
P 5. Carrying out environmental studies
I 6. Operating pollution control equipment
E 7. Cleaning up a polluted lake
I 8. Recycling scrap
P 9. Recycling products
E 10. Cleaning up oil spills