Christmas Express makes wreaths in batch sizes of 15. The cutting & assembly pro

ID: 2430638 • Letter: C

Question

Christmas Express makes wreaths in batch sizes of 15. The cutting & assembly process takes 2 minutes per wreath and the decorating process time is 15 minutes per wreath. It takes 5 minutes to move the wreaths from the cutting & assembly process to the decorating process.

Compute the value-added, non-value-added, and the total lead time of the wreath process.

Value-added lead time:

Non-value-added lead time:

Move time

Within batch wait time

Total lead time

Compute the value-added ratio. Round to one decimal place.
%

Value-added lead time:

Non-value-added lead time:

Move time

Within batch wait time

Total lead time

Explanation / Answer

Value added lead time =2+15

17

Non value added lead time

Move time

5

Within batch wait time 15 x (15-1)

196

Total lead time

218

Value added lead time =2+15

17

Non value added lead time

Move time

5

Within batch wait time 15 x (15-1)

196

Total lead time

218