Christmas Express makes wreaths in batch sizes of 31. The cutting & assembly process takes 5 minutes per wreath and the decorating process time is 10 minutes per wreath. It takes 6 minutes to move the wreaths from the cutting & assembly process to the decorating process. Compute the value-added, non-value-added, and the total lead time of the wreath process. Value-added lead time: Non-value-added lead time: Move time Within batch wait time Total lead time Compute the value-added ratio. Round to one decimal place.Explanation / Answer
Value added leadtime = 15 minutes (cutting & assembly + decorating process time)
Non-value added lead time :
Move time = 6 minutes
within batch wait time = ( total time to perform operations) X ( batch size - 1)
within batch wait time = ( 5 + 10) X ( 31-1)
within batch wait time = 450 minutes
Total lead time = 471 minutes
Value added ratio = Value added lead time / Total lead time
Value added ratio = 15 / 471
Value added ratio = 3.20 %
Related Questions
Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at
drjack9650@gmail.com
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.