Amber Company produces iron table and chair sets. During October, Amber’s costs
ID: 2430785 • Letter: A
Question
Amber Company produces iron table and chair sets. During October, Amber’s costs were as follows:
Required:
a. Calculate the total cost of purchases for October.
b. Compute the direct materials price variance based on quantity purchased. (Indicate the effect of each variance by selecting "F" for favorable, "U" for unfavorable.)
c. Calculate the direct materials quantity variance based on quantity used. (Indicate the effect of each variance by selecting "F" for favorable, "U" for unfavorable.)
d. Compute the standard direct labor rate for October. (Round your answer to 2 decimal places.)
e. Compute the direct labor efficiency variance for October. (Round your intermediate calculation to 2 decimal places. Indicate the effect of each variance by selecting "F" for favorable, "U" for unfavorable.)
Explanation / Answer
a)
Total Cost of Purchase
(A)
Actual Price per lb.
$ 1.80
(B)
Quantitry Purchased
1065000
(A*B)
Total Cost of Purchase
$ 1,917,000.00
b)
Material Price Variance
(
Standard Rate
-
Actual Rate
)
x
Actual Quantity
(
$ 1.60
-
$ 1.80
)
x
1065000
-213000
Variance
213000
Unfavourable-U
c)
Material Quantity Variance
(
Standard Quantity
-
Actual Quantity
)
x
Standard Rate
(
920000
-
950000
)
x
$ 1.60
-48000
Variance
48000
Unfavourable-U
d)
Actual labour hour
7000
Actual rate per Labor hour
$7.00
Actual Cost for labor
49000
Labor Rate variance
5000 F
This means Standard cost at standard rate would be (49000+5000) $54000
Standard rate
(cost at standard rate/actual labor hours)
Standard rate
(54000/7000)
Standard rate per labor hour
$ 7.71
e)
Labour Efficiency Variance
(
Standard Hours
-
Actual Hours
)
x
Standard Rate
(
15000
-
7000
)
x
$ 7.71
61680
Variance
61680
Favourable-F
a)
Total Cost of Purchase
(A)
Actual Price per lb.
$ 1.80
(B)
Quantitry Purchased
1065000
(A*B)
Total Cost of Purchase
$ 1,917,000.00