Tech Inc.is a manufacturer that used traditional costing in the past, where over
ID: 2437169 • Letter: T
Question
Tech Inc.is a manufacturer that used traditional costing in the past, where overhead costs were allocated based on a single predetermined rate using machine hours. The company recently switched to an activity-based costing system using different cost drivers for each of their two activities. Tech Inc. has provided the following data concerning its annual overhead and its activity based costing system:
Product A requires 300 orders and 14,000 machine hours. What is the total overhead cost assigned to Product A using Activity Based Costing?
Activity Cost Pools Total Cost Total Activity Rate Filling Orders $37,800 900 orders $42 per order Order Size $300,000 25,000 machine hours $12 per machine hour TOTAL $337,800Explanation / Answer
Activity Cost Pools Product A Filling Orders 12600 =300*42 Order Size 168000 =14000*12 Total overhead cost assigned 180600 Option 1 is correct
Related Questions
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.