Academic Integrity: tutoring, explanations, and feedback — we don’t complete graded work or submit on a student’s behalf.

On April 1, 2010, Dougherty Inc. entered into a cost-plus-fixed-fee contract to

ID: 2443428 • Letter: O

Question

On April 1, 2010, Dougherty Inc. entered into a cost-plus-fixed-fee contract to construct an electric generator for Altom Corporation. At the contract date, Dougherty estimated that it would take 2 years to complete the project at a cost of $2,300,000. The fixed fee stipulated in the contract is $517,500. Dougherty appropriately accounts for this contract under the percentage-of-completion method. During 2010 Dougherty incurred costs of $920,000 related to the project. The estimated cost at December 31, 2010, to complete the contract is $1,380,000. Dolan was billed $690,000 under the contract.

Complete the schedule below to compute the amount of gross profit to be recognized by Dougherty under the contract for the year ended December 31, 2010.

Explanation / Answer

Contract price [$2,300,000 + $517,500]

$2,817,500

Cost to date

$920,000

Estimated cost

$1,380,000

Total estimated cost

$2,300,000

Estimated gross profit

$517,500

[$2,817,500,000 - $2,300,000]

Percentage of completion [$2,300,000 * 0.40]   

$920,000

                                                                                   

Gross profit recognized 2010             40% of $517,500                                                              = $207,000     

Contract price [$2,300,000 + $517,500]

$2,817,500

Cost to date

$920,000

Estimated cost

$1,380,000

Total estimated cost

$2,300,000

Estimated gross profit

$517,500

[$2,817,500,000 - $2,300,000]

Percentage of completion [$2,300,000 * 0.40]   

$920,000

Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at
drjack9650@gmail.com
Chat Now And Get Quote