Stanley Company has the following information available for October when 3,000 u
ID: 2459949 • Letter: S
Question
Stanley Company has the following information available for October when 3,000 units are produced:
Standard materials cost per unit
3.5 pounds at $4.50 per pound
Actual data for October:
Materials purchased
12,300 pounds at $4.25 per pound.
Materials used
11,750 pounds
The materials usage variance is:
Stanley Company has the following information available for October when 3,000 units are produced:
Standard materials cost per unit
3.5 pounds at $4.50 per pound
Actual data for October:
Materials purchased
12,300 pounds at $4.25 per pound.
Materials used
11,750 pounds
The materials usage variance is:
Explanation / Answer
Material Usage Variance = (Actual Quantity - Standard Quantity) x Standard Price
(11750 -3000*3.5)*4.5 =5625 unfavorable