Academic Integrity: tutoring, explanations, and feedback — we don’t complete graded work or submit on a student’s behalf.

As of the end of June, the job cost sheets at Racing Wheels, Inc., show the foll

ID: 2464832 • Letter: A

Question

As of the end of June, the job cost sheets at Racing Wheels, Inc., show the following total costs accumulated on three custom jobs.

D

Job 102 was started in production in May and the following costs were assigned to it in May: direct materials, $6,000; direct labor, $1,800; and overhead, $900. Jobs 103 and 104 are started in June. Overhead cost is applied with a predetermined rate based on direct labor cost. Jobs 102 and 103 are finished in June, and Job 104 is expected to be finished in July. No raw materials are used indirectly in June. Using this information, answer the following question. (Assume this company's predetermined overhead rate did not change across these months).

What is the cost of the raw materials requisitioned in June for each of the three jobs?

Explanation / Answer

Job 102 = 15000 -6000 = 9000

Job 103 = 33000

Job 104 = 27000