Completed Contract Method versus Percentage-of-Completion Method The Miller Company won a contract to build a shopping center at a price of $240 million The following schedule details the estimated and actual costs of construction and the actual cash collections under the contract: Estimated (Actual) CostsCash Collections of Construction From Customer Year 1 Year 2 Year 3 Year 4 $40,000,000 60,000,000 70,000,000 30,000,000 200,000,000 $48,000,000 60,000,000 60,000,000 72,000,000 $240,000,000 Prepare an income statement for the Miller Company for each year assuming that the company recognizes revenue under the completed contract method Year 1 Year 2 Year 3 Year 4 Total Revenue Construction Cost Net Income Prepare an income statement for the Miller Company for each year assuming that the company recognizes revenue under the percentage-of-completion method Year 1 Year 2 Year 3 Year 4 Total Revenue Construction Cost Net IncomeExplanation / Answer
Net Profit is calculated as under:
Completed contract Method S.No. Detail 1 2 3 4 1 Cost incurred duringthe year $400,00,000 $600,00,000 $700,00,000 $300,00,000 2 Accumulated Cost
At The End $400,00,000 $1000,00,000 $1700,00,000 $2000,00,000 3 Estimated costs to complete
as of year-end $1600,00,000 $1000,00,000 $300,00,000 $0 4 Estimated Total Cost (2+3) $2000,00,000 $2000,00,000 $2000,00,000 $2000,00,000 5 Completion %(2/5) 0.00% 0.00% 0.00% 100.00% 6 Recognized Revenue till
date 240000000*Completion% - - - 2400,00,000 7 Recognized Revenue in year - - - 2400,00,000 8 Billings during the year $0 $0 $0 $0 9 Cash collections during
the year $480,00,000 $600,00,000 $600,00,000 $720,00,000 10 Gross Profit(7-1) $0 $0 $0 $400,00,000
Related Questions
Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at
drjack9650@gmail.com
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.