Talladega Industries, Inc., (TII) developed the following standard costs for dir
ID: 2483591 • Letter: T
Question
Talladega Industries, Inc., (TII) developed the following standard costs for direct material and direct labor for one of their major products, the 10-gallon plastic container.
Standard quantity
Standard price
Direct materials
0.10 pounds
$30 per pound
Direct labor
0.05 hours
$15 per hour
During August, TII produced and sold 10,000 containers using 980 pounds of direct materials at an average cost per pound of $32 and 500 direct labor hours at an average wage of $15.25 per hour.
August's direct material cost variance was:
Select one:
a. $1,960 unfavorable.
b. $600 favorable.
c. $1,360 unfavorable.
d. None of the above is correct.
Standard quantity
Standard price
Direct materials
0.10 pounds
$30 per pound
Direct labor
0.05 hours
$15 per hour
Explanation / Answer
SR 30 AR 32 SQ 1000 AQ 980 direct material cost variance= SC-AC ie= (30*1000)-(32*980) ie= 30000-31360 ie= 1360(A) option c is correct