Dreary Credit Agency uses a standard cost system for the processing of its credi
ID: 2485539 • Letter: D
Question
Dreary Credit Agency uses a standard cost system for the processing of its credit applications. The labor standard at Dreary is 10 applications per 8 hour day at a standard cost of SI 5 per hour. During the last pay period. Dreary's credit agents worked 1,920 hours and processed 2,500 applications. The total labor cost for the agents during this period was $29,184. What was Dreary's labor efficiency variance for this last pay perio d$384 Unfavorabl S816 Favorable $1, 200 Favorable $1,500 FavorableExplanation / Answer
Labour Efficiency Variance = ( Standard Hours- Actual Hours) Standard Rate per Hour (250*8-1920)15 (2000-1920)*15 Labour Efficiency Variance = 1200 F The correct option is C. $ 1200 favourable
Related Questions
Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at
drjack9650@gmail.com
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.