Prokp Co.'s records for April disclosed the following data relating to direct labor: Actual labor cost/payroll for April $18,000 Labor rate variance $3,500 favorable Labor efficiency variance $2,140 unfavorable Actual direct labor hours worked (AQ) 900 Prokp's total flexible budget variance cost for the output in April was: Prokp Co.'s records for April disclosed the following data relating to direct labor: Actual labor cost/payroll for April $18,000 Labor rate variance $3,500 favorable Labor efficiency variance $2,140 unfavorable Actual direct labor hours worked (AQ) 900 Prokp's total flexible budget variance cost for the output in April was:Explanation / Answer
Direct rate variance = ( standard rate - actual rate) Actual hours
3,500 = (x - 20) 900
X = 23.88888888
So flexible budget variance cost = 900 *23.88888 = $21,500
Flexible cost $3500 -$2140 = $1360(F)
Related Questions
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.