part 1 continue (14 marks) 3. A factory has two production departments- Machinin

ID: 2512556 • Letter: P

Question

part 1 continue

(14 marks) 3. A factory has two production departments- Machining and Finishing. The wage rate for the Machining Department is $25 per hr while in the Finishing department the rate is Sas per hr. The administration and selling.overheads are to be absorhed in the job.cost at 20% of the production cost. Distribution should be added to each job according to quotes from outside carriage companies The company wishes to quote for job #400. The following information is available for the job. Overhead absorption rate: Machining Finishing $60.00 $30.00 Direct Material cost Machining Finishing $14,000 a 5 $3,000 Time required Machining Finishing 30 machine hrs 50 man hrs Special Design Distribution $5 000 $10 000

Explanation / Answer

Please hit LIKE button if this helped. For any further explanation, please put your query in comment, will get back to you.

Machining Finishing Total Direct Material 14000 3000 17000 Direct Labor 750 750 1500 25*30 Hour 15*50 Hour Overhead 1800 1500 3300 60*30 Hour 30*50 Hour Total Production Cost 16550 5250 21800 Selling and Admin 20% 3310 1050 4360 Distribution 10000 Special Design 5000 Total Cost 41160 Profit Margin 25% 10290 Quot Price 51450